Task
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Travel to Sparta
xx
Site tour -
xx
last minute changes with Kerkman
xx
National Guard briefing/training
xx
Geosynthetic pre-test
xx
Tire chip pre-test
xx
Build wooden mats
xx
Build PVD pipe facine
xx
Site characterization - wooded trail
xx
Construction - woods trail
xx xx
Tests and evaluation - woods trail
xx xx
Characterization - slopes
xx
Construction - slopes
xx xx
Test and evaluation - slopes
xx xx
Remove mats for use on corners
xx
Characterization - corners
xx
Construction - corners
xx xx
Test and evaluation - corners
xx xx
Site cleanup, section removal, shipping
xx xx xx xx xx xx
We will likely work in three crews:
Site chararacterization - Jeff as CRREL Representative
Construction - Maureen/Jeff as CRREL Representatives
Performance evaluation - Karen as CRREL Representative
Sally/Jim will roam and act as go-for, put out fires, etc.
Figure F7. Proposed schedule.
66